2005 Capital Projects
In order to view these documents, you will need to have the Adobe Acrobat Reader plug-in installed. You can download Acrobat Reader for free by clicking on the icon to the right. |
Capital Project Title |
Capital Project No. |
Capital Project Price |
Resolution Approval No. |
| White River Purification Plant 84-MGD Filter Upgrade |
2005-003 |
$799,000 |
No. 2 |
| White River Purification Plant 84-MGD Filter Upgrade (CHANGE ORDER REQUEST FOR $100,000 DECREASE) |
2005-003 CHANGE ORDER |
$699,000 |
No. 16 |
| White River Boilers |
2005-008 |
$274,579 |
No. 16 |
| White River North Wells & Well Collecting Lines |
2005-027 |
$1,048,600 |
No. 7 |
| White River North Well Water Transmission Main |
2005-030 |
$1,349,000 |
No. 2 |
| Geist Groundwater Plant Expansion |
2005-048 |
$3,891,967 |
No. 7 |
| South Well Field Station Finish Water Reservoir #2 |
2005-056 |
$711,000 |
No. 2 |
| South Well Field Station Finish Water Reservoir #2 (CHANGE ORDER REQUEST FOR $150,000 DECREASE) |
2005-056 CHANGE ORDER |
$561,000 |
No. 16 |
| Lizton Elevated Tank |
2005-071 |
$2,359,500 |
No. 2 |
| Terry Airport Elevated Tank |
2005-072A |
$2,320,500 |
No. 2 |
| Terry Airport Main |
2005-072B |
$575,427 |
No. 2 |
| Terry Airport Main (CHANGE ORDER REQUEST FOR $211,091 INCREASE) |
2005-072B-CHANGE ORDER |
$786,518 |
No. 11 |
| Terry Airport Main (CHANGE ORDER REQUEST FOR $116,400 INCREASE) |
2005-072B AMENDED CHANGE ORDER |
$902,918 |
No. 18 |
| McCordsville Elevated Tank |
2005-073 |
$2,484,000 |
No. 2 |
| New Palestine Elevated Tank |
2005-074 |
$385,500 |
No. 2 |
| New Palestine Elevated Tank |
2005-074 |
|
|
| New Palestine Elevated Tank (CHANGE ORDER REQUEST FOR $34,925 |
2005-074- CHANGE ORDER |
$1,553,675 |
No. 11 |
| Cooper Road Reinforcement Main |
2005-099K |
$55,510 |
No. 7 |
| CR 300S-Michigan RD to CR 875E |
2005-099U |
$1,019,651 |
No. 7 |
| CR 300S-Michigan RD to CR 875E (CHANGE ORDER REQUEST FOR $55,675 INCREASE) |
2005-099U- CHANGE ORDER |
$1,075,326 |
No. 11 |
| CR 300S-Michigan RD to CR 875E (CHANGE ORDER REQUEST FOR $116,400 DECREASE) |
2005-099U CHANGE ORDER |
$958,926 |
No. 18 |
| Moore Road |
2005-099Y |
$144,392 |
No. 7 |
| Moore Road (CHANGE ORDER REQUEST FOR $55,675 DECREASE) |
2005-099Y- CHANGE ORDER |
$88,717 |
No. 11 |
| SR 38 @ Harbour Water |
2005-099DD |
$24,603 |
No. 7 |
| Canal Cleaning-Aqueduct to Intake Phase II |
2005-100 |
$459,400 |
No. 7 |
| Geist Concrete Steps |
2005-101 |
$18,490 |
No. 18 |
| Well Monitoring Program |
2005-102 |
$55,000 |
No. 7 |
| Preliminary Design of WRPP Intake on White River |
2005-103 |
$210,000 |
No. 7 |
| White River Intake Station Concrete Refurbishment |
2005-117A |
$90,000 |
No. 2 |
| WR Intake-Traveling Screen Automatic Wash System |
2005-117E |
$24,000 |
No. 7 |
| White River Rapid Mix Upgrade |
2005-117M |
$802,000 |
No. 18 |
| SWF Heat Pump Replacement |
2005-143 |
$52,000 |
No. 2 |
| Avon District-Additional Water |
2005-150 |
$231,000 |
No. 18 |
| Lafayette District Booster Station |
2005-151 |
$900,000 |
No. 45 |
| G.O. Hot & Return Water Piping |
2005-152A |
$40,000 |
No. 18 |
| G.O. Boiler Upgrade |
2005-152C |
$79,000 |
No. 18 |
| Bleeder Valve Installation |
2005-155 |
$210,000 |
No. 11 |
| Security |
2005-158A-158I |
$532,090 |
No. 18 |
| Install Safety system from access to ceiling & light at Riverside |
2005-158Y |
$25,000 |
No. 2 |
| Redundant Communications |
2005-165A |
$31,100 |
No. 7 |
| Infrastructure Upgrade |
2005-165B |
$86,300 |
No. 7 |
| Option 11C Phone Switch |
2005-165C |
$62,100 |
No. 7 |
| SCADA Communications Upgrade |
2005-165F |
$331,000 |
No. 18 |
| Filter Redesign |
2005-168 |
$225,000 |
No. 2 |
| Reservoir & Tower Refurbishments |
2005-169 |
$90,000 |
No. 2 |
| Building, Pump Station & Treatment Plant Refurbishment |
2005-170 |
$360,000 |
No. 2 |
| Building, Pump Station & Treatment Plant Refurbishment (CHANGE ORDER REQUEST FOR $100,000 INCREASE) |
2005-170 CHANGE ORDER |
$725,000 |
No. 16 |
| Asbestos & Lead Paint Removal |
2005-171 |
$10,000 |
No. 2 |
| Asbestos & Lead Paint Removal (CHANGE ORDER REQUEST FOR $40,000) |
2005-171 (CHANGE ORDER) |
$50,000 |
No. 11 |
| WR Residuals |
2005-172 |
$115,000 |
No. 18 |
| Darlington Elevated Tank Refurbishments |
2005-200 |
$51,000 |
No. 7 |
| Harbour Elevated Tank Refurbishment |
2005-201 |
$39,500 |
No. 7 |
| Underground Infrastructure-B, C, E, F, I, & Laydown Valves |
2005-303C |
$6,670,000 |
No. 45 |
| Underground Growth-D, G, L,& Easements |
2005-304D |
$4,300,000 |
No. 45 |
|
|
|
|
|
|