2002 Capital Projects
In order to view these documents, you will need to have the Adobe Acrobat Reader plug-in installed. You can download Acrobat Reader for free by clicking on the icon to the right. |
| Capital Project Title |
Capital Project # |
Capital Project Price |
| Crossing System for Temporary Hoses |
2002-106 |
$29,100 |
| Mezzanine for Carpenters Shop |
2002-108 |
$9,700 |
| Mezzanine for Storage Barn |
2002-110 |
$26,675 |
| Subsite Tracing Machine |
2002-123 |
$6,062 |
| RD400 Locating Equipment |
2002-147 |
$13,338 |
| Acton Main (B-job) |
2002-202 |
$795,000 |
| SWF Well Line Throttle Valves |
2002-214 |
$102,000 |
| WR Increase Well Water |
2002-216 |
$560,000 |
| TWM Generator Automatic Control |
2002-217 |
$72,750 |
| Zionsville Booster Station |
2002-223 |
$60,625 |
| Update 1985 Water Resource Plan |
2002-224 |
$185,000 |
| Water Supply to MCRWC (CANCELLED) |
2002-225 |
$9,226 |
| FC Well #11 Upgrade |
2002-227 |
$60,500 |
| WR Chemical Conversion |
2002-233 |
$4,220,000 |
| FC Electrical Upgrade |
2002-243 |
$1,333,700 |
| NPDES Outfalls |
2002-245 |
$101,400 |
| WR Basin Flow Meters |
2002-247 |
$110,500 |
| WR Upgrade 2 Filters per Year |
2002-248 |
$577,700 |
| Geist Dam Radio-controlled Operator |
2002-250 |
$38,800 |
| WR Washwater Pump |
2002-254 |
$86,100 |
| RS Well line Throttle Valve |
2002-260 |
$27,000 |
| FC Well #17 Check Valve |
2002-260-02 |
$7,200 |
| WR Transformers |
2002-263 |
$100,000 |
| Phone Switch |
2002-871 |
$298,037 |
| FC Washwater Pump Motor Starter |
2002-287 |
$14,550 |
| WRN Chlorine Contact Basin |
2002-290 |
$120,000 |
| 300North Lightning Protection |
2002-404 |
$12,200 |
| FC Basin Chains & Sprockets |
2002-405 |
$24,250 |
| Geist SS Impellers |
2002-406 |
$8,487 |
| Morse Service Building Roof Replacement |
2002-408 |
$9,700 |
| TWM Flock Drive Replacement |
2002-409 |
$26,675 |
| WR Basin Chains & Sprockets |
2002-410-A |
$30,313 |
| WR 84MG Floor Tile Replacement |
2002-410-B |
$8,488 |
| WR Intake Doors |
2002-410-C |
$7,275 |
| WR Elevator Upgrade |
2002-410-D |
$29,100 |
| WR Underground Power Feed Replacement |
2002-410-E |
$30,000 |
| WR 84MG Plant Ceiling |
2002-410-F |
$121,250 |
| WR Junction Vault Design |
2002-410-G |
$30,312 |
| WRN Emergency Power |
2002-411-08 |
$36,375 |
| WRN Filter Valve Controller |
2002-411-09 |
$14,550 |
| 86th St. & I-465 (B-job) |
2002-B-02-004 |
$75,055 |
| 56th St. Reed Road to I-465 (B-Job) |
2002-B-02-005 |
$161,142 |
| 30th St. & Lafayette Rd.(C-job) |
2002-C-02-011 |
$337,018 |
| Eagle Creek Park Main Ext. |
2002-D-02-272 |
$43,796 |
| GO Boiler Replacement |
2002-E-01 |
$97,960 |
| WR Filter # 7 |
2002-E-02 |
$116,715 |
| Rocky Ripple (K-job) |
2002-K-01-078 |
$3,200,000 |
| Ravenswood (K-job) |
2002-K-02-032 |
$2,205,932 |
| McFarland Road at Montgomery Ave |
2002-202A-B-02-001 |
$19,000 |
| 11th St. at Edgewood Dr. |
2002-202A-B-02-002 |
$17,500 |
| Combs Road South of Silverado |
2002-202A-B-02-003 |
$18,500 |
| Franklin Road & 42nd St |
2002-202A-B-02-008 |
$20,000 |
| Hayworth Road |
2002-203-E-02-013 |
$36,000 |
| 116th St. Sand Creek Drive to Hoosier Road |
2002-203-E-02-024 |
$70,000 |
| Springmill Road Bridges north of 116th St. |
2002-203-E-01-005 |
$85,000 |
| Brisbane & Manning Barrett Law Relocations |
2002-203-E-01-023 |
$40,818 |
| 96th St. $ Shelbourne Hydrant Location |
2002-203-E-02-049 |
$5,012 |
| 116th St. and Brooks School Road |
2002-203-E-02-038 |
$20,815 |
| 24th St. & Talbot |
2002-203-E-02-030 |
$8,207 |
| McFarland Road at Wetnight Ditch |
2002-203-E-02-027 |
$44,059 |
| Allisonville Road Bridge 12100N |
2002-203-E-02-008 |
$39,938 |
| 113th St. & Florida Road |
2002-204-G-02-005 |
$325,000 |
| Walcott Street |
2002-204-G-02-006 |
$7,000 |
| Graham Road |
2002-204-G-02-003 |
$4,000 |
| 56th St: west of I-65 |
2002-204-G-02-004 |
$3,500 |
| Butler Ave& 70th St. |
2002-204-G-02-008 |
$6,200 |
| Camby Road |
2002-206-I-02-001 |
$15,000 |
| US 421 Phase 1: 96th St. to 106th St. |
2002-210-F-01-002 |
$50,000 |
| W. Washington St: Raceway Rd. to Research Way |
2002-210-F-00-002 |
$70,000 |
| CSX Bridge over US 136 |
2002-210-F-01-003 |
$44,263 |
| Tribley Court-HWC |
2002-213-C-02-001 |
$30,312 |
| Yellowood Circle-HWC |
2002-213-C-02-002 |
$33,950 |
| Amhurst Circle-HWC |
2002-213-C-02-003 |
$30,312 |
| Sassafras Circle-HWC |
2002-213-C-02-004 |
$30,312 |
| 21st St: Rockford St.to German Church Road |
2002-213-C-02-006 |
$205,000 |
| Gladstone Ave: 30th St to RR |
2002-213-C-02-007 |
$145,500 |
| Massachusetts Ave: Rural St to a pt west |
2002-213-C-02-008 |
$54,600 |
| Pine St. & 9th St |
2002-213-C-02-012 |
$26,885 |
| Diamond Pointe |
2002-213-C-02-013 |
$18,500 |
|
|